Wednesday, November 11, 2009 at 4:53 p.m.
Read more: Local, Tourism, I 675, Mdot, Michigan Department of Transportation, Work, Road, Repair, Construction
Overall, work on SB I-675 lanes is approximately 95% complete.
Work on southbound lanes is expected to be completed as scheduled by early December 2009.
- Northbound I-675 construction is scheduled for 2010.
- I-675 southbound lanes from Tittabawassee Road south to Michigan Avenue in Saginaw County have reopened.
- Southbound lanes remain closed from Michigan Avenue south to 5th and 6th Streets. This area is expected to open by Nov. 15.
- One southbound lane remains open from the 5th / 6th Street exit south to the I-675 south junction with I-75.
- 14th Street under I-675 is now open.
- Crews are pouring the remaining spans of the ramp from M-58 to southbound I-675. This ramp will soon reopen.
- Work on the Henry Marsh Bridge in downtown Saginaw is expected to be completed by November 13. Crews continue pouring the bridge railings.
- Once work is completed and the southbound lanes across the Henry Marsh Bridge reopen, crews will begin work on the northbound lanes across the bridge.
- Northbound lanes across the Henry Marsh Bridge are expected to close in early February 2009.
- I-675/I-75 South Junction: I-675 southbound to I-75 northbound ramp is now open.
Northbound I-675:
- One northbound lane is open from the Henry Marsh Bridge in downtown Saginaw north to Shattuck Road.